Perris Boulevard Widening Construction Status Updates

Construction Status Update 9/1/15 – 9/30/15

  • Contractor will be installing traffic striping on Perris Boulevard from 9/10/15 to 9/20/15.
  • New traffic signal light at Perris Boulevard and Pico Vista Drive will be turned on once traffic striping is in place.
  • Contractor will be performing all punch list items in the month of September to complete the project.

Please drive safely through the construction zone

Construction Status Update 8/3/15-8/29/15

  • Contractor continues working on the street median that include stamped concrete finish.
  • Roadway paving continues with final surface paving is scheduled for the week of 8/10/15 to 8/13/15.
  • The installation of traffic signal pole at Perris Boulevard and Pico Vista Drive is set for 8/14/15 to 8/17/15.
  • Installation of traffic striping is set for the week of 8/17/15 to 8/26/15.

Please drive safely through the construction site and obey the speed limit of 30 MPH through the project limits.

Construction Status Update 7/13/15 – 7/31/15

  • Contractor continues working on the street median that include median curb and stamped concrete finish.
  • Roadway paving is also underway with the construction of base materials. Final surface paving is scheduled for the week 7/28/15 to 7/31/15. 
  • The installation of traffic signal pole at Perris Boulevard and Pico Vista Drive is set for 7/29/15 to 7/31/15.

Please drive safely through the construction site and obey speed limit of 30 MPH through the project limits.

Construction Status Update 6/15/15 - 6/26/15

  • Contractor shifted southbound traffic onto new pavement next to the curb and gutter.
  • Construction will include asphalt removal in the median area from Ironwood to north end of project limit. 
  • Concrete curb will be formed in the median area. Please follow the construction signs and delineators.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.
  • Please obey the construction speed limit of 30 MPH through the project limits.

Please drive safely through the construction zone.

Construction Status Update 6/1/15 - 6/12/15

  • Construction will include asphalt pavement.
  • Complete hydro seeding on slopes along Perris Boulevard.
  • The week of June 8, southbound traffic is scheduled to be shifted onto new pavement next to the curb and gutter. Asphalt removal will then begin in the median area.  Please follow the construction signs and delineators.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.
  • Please obey the construction speed limit of 30 MPH through the project limits.

Please drive safely through the construction zone.

Construction Status Update 5/18/15 - 5/29/15

  • Construction will include concrete and asphalt work, as well as hydro seeding.
  • The week of May 26, southbound traffic is scheduled to be shifted onto new pavement next to the curb and gutter. Asphalt removal will then begin in the median area.  Please follow the construction signs and delineators.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.
  • Please obey the construction speed limit of 30 MPH through the project limits.

Construction Status Update 5/4/15 - 5/15/15

  • Construction will generally be occurring on the west side of the roadway. Construction will include concrete work and asphalt pavement.
  • The week of May 11, southbound traffic is scheduled to be shifted onto new pavement next to the curb and gutter.  Please follow the construction signs and delineators.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.
  • Please obey the construction speed limit of 30 MPH through the project limits.

Please drive safely through the construction zone.

Construction Status Update 4/20/15 - 5/1/15

  • Traffic has been shifted through the project limits. Travelling northbound, after crossing Ironwood Avenue, motorists are shifted against the right (eastern) curb and narrowed to one lane, until north of Pico Vista Way. North of this point, the two existing northbound lanes are available. Travelling southbound from Manzanita Avenue, traffic shifts toward the center of the roadway and narrows to one lane, through the project limits to Ironwood Avenue. Construction will generally be occurring on the west side of the roadway. Construction will include curb and gutter, sidewalks, driveways, and pavement. Please follow the construction signs and delineators.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.
  • Please obey the construction speed limit of 30 MPH through the project limits.

Please drive safely through the construction zone.

Construction Status Update 4/6/15 - 4/17/15

  • Traffic has been shifted throughout the project limits. Travelling northbound, after crossing Ironwood Avenue, motorists are shifted against the right (eastern) curb and narrowed to one lane, until north of Pico Vista Way.  North of this point, the two existing northbound lanes are available. Travelling southbound from Manzanita Avenue, traffic shifts toward the center of the roadway and narrows to one lane, throughout the project limits to Ironwood Avenue. Construction will be occurring on the west side of the roadway. Construction will include earthwork, curb and gutter, sidewalks, driveways, and pavement. Please follow the construction signs and delineators.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.
  • Please obey the construction speed limit of 30 MPH through the project limits.

Please drive safely through the construction zone.

Construction Status Update 3/23/15 - 4/3/15

  • On March 25-26, traffic will be shifted throughout the project limits.  Travelling northbound, after crossing Ironwood Avenue, motorists will be shifted against the right (eastern) curb, and narrowed to one lane, until north of Pico Vista Way, where the existing two northbound lanes will be available. Travelling southbound from Manzanita Avenue, traffic will be shifted toward the center of the roadway, and narrowed to one lane, throughout the project limits, to Ironwood Avenue.  Construction will be occurring on the west side of the roadway.  Construction will include curb and gutter, sidewalks, driveways, and pavement.  Please follow the construction signs and delineators.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Update 3/9/15 - 3/20/15

  • Motorists wishing to drop off students at North Ridge School or wishing to turn right on Kalmia Avenue will make a slight right onto the new pavement before reaching Kalmia Avenue. Please drive carefully. U-Turns can be made at Luxury Street and Pico Vista Way. Please follow the construction signs and delineators.
  • Utility work is on-going replacing poles and wires at the north end of the project.
  • Pavement and concrete work is on-going on the east and west sides of Perris Boulevard. Expect intermittent lane closures.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Update 2/23/15 - 3/6/15

  • Motorists wishing to drop off students at North Ridge School or wishing to turn right on Kalmia Avenue will make a slight right onto the new pavement before reaching Kalmia Avenue.  Please drive carefully. U-Turns can be made at Luxury Street and Pico Vista Way. Please follow the construction signs and delineators.
  • Utility work is on-going replacing poles and wires at the north end of the project.
  • Pavement and concrete work is on-going on the east and west sides of Perris Boulevard. Expect intermittent lane closures.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Update 2/9/15 - 2/20/15

  • Motorists wishing to drop off students at North Ridge School or wishing to turn right on Kalmia Avenue will make a slight right onto the new pavement before reaching Kalmia Avenue. The week of February 9th, northbound traffic at Ironwood will be shifted against the eastern curb. Please drive carefully. U-Turns can be made at Luxury Street and Pico Vista Way. Please follow the construction signs and delineators.
  • Utility work is on-going replacing poles and wires at the north end of the project.
  • Pavement and concrete work is on-going on the east and west sides of Perris Boulevard. Expect intermittent lane closures.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Update 1/26/15 - 2/6/15

  • New northbound traffic patterns are in effect starting at Ironwood Avenue until Feb 5. Motorists wishing to drop off students at North Ridge School or wishing to turn right on Kalmia Avenue will make a slight right onto the new pavement before reaching Kalmia Avenue. Beginning Feb. 5, northbound traffic at Ironwood will be shifted against the eastern curb. Please drive carefully. U-Turns can be made at Luxury Street and Pico Vista Way. Please follow the construction signs and delineators.
  • Utility work is on-going replacing poles and wires at the north end of the project.
  • Pavement and concrete work is on-going on the east side of Perris Boulevard. Expect intermittent lane closures.
  • Retaining wall construction is underway on the west side of Perris Boulevard near Pico Vista Way.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Update 1/12/15 - 1/23/15

  • New northbound traffic patterns are in effect starting at Ironwood Avenue. Motorists wishing to drop off students at North Ridge School or wishing to turn right on Kalmia Avenue will make a slight right onto the new pavement before reaching Kalmia Avenue. Northbound traffic has also been shifted onto new pavement from just north of Kalmia Avenue to north of Pico Vista Way. Please drive carefully. U-Turns can be made at Luxury Street and Pico Vista Way. Please follow the construction signs and delineators.
  • Pavement work is on-going on the east side of Perris Boulevard. Expect intermittent lane closures.
  • Retaining wall construction is underway on the west side of Perris Boulevard near Pico Vista Way.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

2014 Updates (Click to open)

Construction Status Update 12/22/14 - 1/9/15

  • New traffic patterns are in effect at Ironwood Avenue. Northbound traffic has been shifted onto new pavement from Kalmia Avenue to North of Pico Vista Way. Please drive carefully. U-Turns can be made at Luxury Street and Pico Vista Way. Please follow the construction signs and delineators.
  • Pavement work is on-going on the east side of Perris Boulevard. Expect intermittent lane closures.
  • Retaining wall construction is underway on the west side of Perris Boulevard near Pico Vista Way.
  • Signal work is underway at Kalmia Avenue.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised. Please drive safely through the construction zone.

Construction Status Update 12/8/14 - 12/19/14

  • Northbound traffic has been shifted onto new pavement from Kalmia Avenue to North of Pico Vista Way.  Please drive carefully.  U-Turns can be made at Luxury Street and Pico Vista Way.  Please follow the construction signs and delineators.
  • Concrete work is on-going along the east side of Perris Boulevard.  Expect intermittent lane closures.
  • Retaining wall construction is underway on the west side of Perris Boulevard near Pico Vista Way.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Update 11/17/14 - 12/5/14

  • There will be a full closure of Jaclyn Avenue from Perris Boulevard to Coleman Street from Nov. 3 to Nov. 26 to reconstruct the intersection at Perris Boulevard. Detours will be provided and clearly marked. When this work is complete, some traffic patterns will be changed. Please follow the construction signs and delineators.
  • Grading, paving, and concrete work is on-going along the east side of Perris Boulevard. Expect intermittent lane closures.
  • Retaining wall construction is underway on the west side of Perris Boulevard near Pico Vista Way.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound north of Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Update 10/29/14-11/14/14

  • There will be a full closure of Jaclyn Avenue from Perris Boulevard to Coleman Street from Nov. 3 to Nov. 26 to reconstruct the intersection at Perris Boulevard. Detours will be provided and clearly marked.
  • Grading, paving, and concrete work is on-going along the east side of Perris Boulevard. Expect intermittent lane closures.
  • Retaining wall construction is underway on the west side of Perris Boulevard near Pico Vista Way.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound near Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Update 10/20/14-10/31/14

  • The contractor anticipates closing a 160 foot-long section of Jaclyn Avenue from Perris Boulevard to Coleman Street from Nov. 3 to Nov. 26 to reconstruct the intersection at Perris Boulevard. A detour will be provided.
  • Grading work is on-going along the east side of Perris Boulevard. Expect intermittent lane closures.
  • Excavation is underway for retaining walls.
  • Curb & gutter and sidewalk construction are scheduled to begin.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound near Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Update 10/6/2014 – 10/17/2014

  • The contractor anticipates closing a 160 foot-long section of Jaclyn Avenue from Perris Boulevard to Coleman Street from Nov. 3 to Nov. 26 to reconstruct the intersection at Perris Boulevard. A detour will be provided.
  • Grading work on-going along the east side of Perris Boulevard.
  • Expect intermittent lane closures for soil excavation and storm drain construction.
  • Utility work will continue:
    • Gas Company, Eastern Municipal Water District, and Verizon staff continues to make progress relocating their lines.
    • The contractor continues to make good progress in locating other existing utilities and will begin drilling signal pole foundations and performing horizontal boring to connect the signals.
  • Excavation is underway for retaining walls.
  • Curb and gutter installation is scheduled to begin.
  • Traffic control delineators have been placed along the roadway and changeable message signs have been installed northbound near Ironwood Avenue and Southbound near Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Updates 9/22/2014 – 10/03/2014

  • Site specific grading work on-going along east side of Perris Boulevard.
  • Expect intermittent lane closures for soil excavation and storm drain construction.
  • Utility work will continue:
    • Gas Company and Water District staff continues to make progress relocating their lines.
    • The Contractor continues to make good progress in locating other existing utilities and will begin drilling signal pole foundations.
  • Exploratory work will continue for retaining walls.
  • Traffic control delineators have been placed along most of the roadway while utility and surveying work is underway.
  • Changeable message signs have been installed northbound near Ironwood Avenue and Southbound near Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Updates 9/8/2014 – 9/19/2014

  • Expect intermittent lane closures for soil excavation and storm drain construction.
  • Utility work will continue:
    • The Gas Company and Water Company will be relocating some of their lines.
    • Exploratory work will be taking place to locate other existing utilities.
  • Exploratory work will continue for retaining walls.
  • Traffic control delineators have been placed along most of the roadway while utility and surveying work is underway.

Changeable message signs have been installed northbound near Ironwood Avenue and Southbound near Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Updates 8/25/2014 – 9/5/2014

  • Expect intermittent lane closures for utility work. Flagmen will be present.
    • The Gas Company and water company will be relocating some of their lines.
    • Exploratory work will be taking place to locate other existing utilities.
  • Exploratory work for retaining walls.
  • Traffic control delineators have been placed along most of the roadway while utility and surveying work is underway.
  • Changeable message signs have been installed northbound near Ironwood Avenue and Southbound near Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.

Construction Status Updates 8/4/2014 – 8/22/2014

  • Intermittent lane closures for utility work. Flagmen will be present.
    • The Gas Company will be relocating some of their lines.
    • Exploratory work will be taking place to locate other existing utilities.
  • Traffic control delineators have been placed along most of the roadway while utility and surveying work is underway.
  • Changeable message signs have been installed northbound near Ironwood Avenue and Southbound near Manzanita Avenue to keep motorists advised.

Please drive safely through the construction zone.